No Client Location Application Gas volume (Temp.) Quantity Completion date Equipment Scope of supply
1 GS E&R GS E&R Banwol Coal Power Plant Coal Fired Boiler Dry-EP Retrofit #2 (200 t/h) 7,680 Am3/min, (150℃) 1 July, 2017 Dry-EP EPC
2 DAEWOO E&C / HALLA E&E MOROCCO JORF LASFAR Power Plant TPP Coal Fired Boiler EP Maintenance #5 (350 MW) 31,239 Am3/min, (149℃) 1 Mar, 2016 Dry-EP EC
3 EWP EWP Donghae Bio Power Plant TPP Fired Boiler EP Retrofit EP Retrofit #1 (200 MW) 18,050 Am3/min, (150℃) 1 Sep, 2015 Dry-EP EP
4 A-Jeon E&C KOEN Hadong Coal Power Plant TPP Coal Fired Boiler #2, #2 Field (500 MW) 47,000 Am3/min, (125℃) 1 May, 2015 Dry-EP PC
5 Hyundai Energy Yeosu Industrial Complex Coal Fired Boiler EP #1, #2 (350 t/h) 8,772 Am3/min, (135℃) 2 Jan, 2012 Dry-EP PC
6 POSCO POSCO Gwangyang Factory #2 Hot Strip Mill Fume Exhaust System Wet-EP 7,000 Am3/min (50℃) 1 Apr, 2011 Wet-EP EPC
7 POSCO POSCO Gwangyang Thick Plate Factory Finishing Mill Fume Exhaust System 4,000 Am3/min (60℃) 1 Mar, 2010 Wet-EP EPC
8 DONGBU Steel DONGBU Steel Dangjin Factory Finishing Mill Fume Exhaust System 4,500 Am3/min (40ºC) 1 Jun, 2009 Wet-EP EPC
  • Client
    GS E&R / 아전이엔씨
    Location
    GS E&R 반월발전처
    Application
    Coal Fired Boiler EP Retrofit #2 (200 t/h)
    Gas volume (Temp.)
    7,680 Am3/min, (150℃)
    Quantity : 1 Completion date : 2017.07 Equipment : Dry-EP Scope of supply : EPC
  • Client
    대우건설 / 한라산업개발㈜
    Location
    모로코 JORF LASFAR 발전소
    Application
    TPP Coal Fired Boiler EP Maintenance #5 (350 MW)
    Gas volume (Temp.)
    31,239 Am3/min, (149℃)
    Quantity : 1 Completion date : 2016.03 Equipment : Dry-EP Scope of supply : EC
  • Client
    한국동서발전
    Location
    한국동서발전 동해바이오화력본부
    Application
    TPP Fired Boiler EP Retrofit EP Retrofit #1 (200 MW)
    Gas volume (Temp.)
    18,050 Am3/min, (150℃)
    Quantity : 1 Completion date : 2015.09 Equipment : Dry-EP Scope of supply : EP
  • Client
    아전이엔씨㈜
    Location
    한국남동발전 하동화력본부
    Application
    TPP Coal Fired Boiler #2, #2 Field (500 MW)
    Gas volume (Temp.)
    47,000 Am3/min, (125℃)
    Quantity : 1 Completion date : 2015.05 Equipment : Dry-EP Scope of supply : PC
  • Client
    현대에너지㈜
    Location
    여수집단에너지
    Application
    Coal Fired Boiler EP #1, #2 (350 t/h)
    Gas volume (Temp.)
    8,772 Am3/min, (135℃)
    Quantity : 2 Completion date : 2012.01 Equipment : Dry-EP Scope of supply : PC
  • Client
    포스코
    Location
    광양공장
    Application
    #2 Hot Strip Mill Fume Exhaust System
    Gas volume (Temp.)
    7,000 Am3/min, (50℃)
    Quantity : 1 Completion date : 2011.04 Equipment : Wet-EP Scope of supply : EPC
  • Client
    포스코
    Location
    광양공장
    Application
    Thick Plate Factory Finishing Mill Fume Exhaust System
    Gas volume (Temp.)
    4,000 Am3/min, (60℃)
    Quantity : 1 Completion date : 2010.03 Equipment : Wet-EP Scope of supply : EPC
  • Client
    동부제철(주)
    Location
    당진공장
    Application
    Finishing Mill Fume Exhaust System
    Gas volume (Temp.)
    4,500 Am3/min, (40ºC)
    Quantity : 1 Completion date : 2009.06 Equipment : Wet-EP Scope of supply : EPC